Open Data Schema for Energy

Grid Capacity / Connection Status

Grid access is the binding constraint on new generation in South Africa. ODS-E provides asset-metadata fields to track the grid connection lifecycle, allocated capacity, and GCAR milestones.

Context

The SAETA “Policy to Power” report describes the GCAR framework introducing 3 milestones (pre-feasibility, capacity reservation, capacity allocation) to structure the queue and prevent speculative lock-up. The NTCSA must add 14,500km of new lines and 210 transformers by 2034. Non-discriminatory grid access is foundational to the SAWEM (Actions 5, 8).

Asset Metadata Fields (under location)

Field Type Description
connection_status enum: applied, pre_feasibility, reserved, allocated, connected, decommissioned Current status in the grid connection lifecycle
allocated_capacity_kw number >= 0 Grid capacity allocated to this asset
connection_agreement_ref string Connection or use-of-system agreement reference
grid_access_queue_date string (date) Date the asset entered the capacity allocation queue
gcar_milestone enum: pre_feasibility, capacity_reservation, capacity_allocation Current GCAR milestone achieved

Usage Notes

Example

{
  "asset_id": "NCAPE-SOLAR-GEN-12",
  "location": {
    "latitude": -31.42,
    "longitude": 19.08,
    "timezone": "Africa/Johannesburg",
    "country_code": "ZA",
    "municipality_id": "za.nc.hantam",
    "voltage_level": "MV",
    "connection_point_id": "ESKOM-TX-KLEINZEE-33KV-F04",
    "connection_status": "allocated",
    "allocated_capacity_kw": 75000,
    "connection_agreement_ref": "COSA-NTCSA-2025-NCape-0172",
    "grid_access_queue_date": "2024-06-15",
    "gcar_milestone": "capacity_allocation"
  },
  "capacity_kw": 80000,
  "oem": "LONGi",
  "asset_type": "solar_pv",
  "commissioning_date": "2026-09-01"
}